Complexity-based risk decision framework for cost overrun using fuzzy Bayesian network

delete2023-03-12
delete1
delete
OA
AI
F
Farman Afzal *
F
Fahim Afzal *
D
Danish Junaid
I
Imran Ahmed Shah
Y
Yunfei Shao
DOI:10.1007/s00500-023-07983-7delete
delete原文链接
delete原文求助
delete分享
delete收藏
摘要

摘要

En 中文
This study adheres to find important complexity-risk interdependent causes of cost overrun in infrastructure transport projects rather considering an independent state of project risk. Aiming for addressing cost overrun problem to facilitate decision-makers, a hierarchical breakdown structure of complex elements and complexity-driven risk factors at different levels of severity is conceptualized along with their interdependency network of key relationships. In this work, an integrated approach of fuzzy logic with the Bayesian belief network is employed for cost-risk assessment while assuming linguistic scales of likelihood and consequences parameters. The simulated results of cost-risk decision framework imply that poor design issues, increase in material prices and delay in relocating facilities show higher complexity-risk dependency and increase the risk of cost overrun in complex projects. This study contributes to the body of knowledge by providing a practical hybrid risk decision framework to identify and evaluate the key complexity-risk interdependencies in underline relations to the cost overrun problem in construction.
Keyword:
Risk assessment
Cost overrun
Complexity-risk interdependency
Fuzzy logic
Bayesian network
Construction projects

期刊

Soft Computing 封面图
Soft Computing
IF:
2.5
论文数:
1.0W
被引数:
2.1W

机构

H
Hohai University
学者数:
2.3W
论文数: 1.8W
被引数: 2.1W
U
university of engineering & technology lahore
学者数:
2.7K
论文数: 2.2K
被引数: 0
引用论文

引用论文

Blood Lead Levels in NASCAR Nextel Cup Teams
err2006-02-01
err0
PREAI
errJoseph O'Neil; Gregory Steele; C. Scott McNair; Matthew M. Matusiak; Jyl Madlem
err分享
err收藏
Amisulpride prevents nausea and vomiting associated with highly emetogenic chemotherapy: a randomised, double-blind, placebo-controlled, dose-ranging trial
err2018-11-28
err0
PREAI
errJ. Herrstedt; Y. Summers; K. Jordan; J. von Pawel; A. H. Jakobsen; M. Ewertz; S. Chan; J. D. Naik; M. Karthaus; S. Dubey; R. Davis; G. M. Fox
err分享
err收藏
Network theory-based analysis of risk interactions in large engineering projects
err2012-10-01
err147
errOAAI
errFang, Chao; Marle, Franck; Zio, Enrico; Bocquet, Jean-Claude
err分享
err收藏
err分享
err收藏
Risk assessment model selection in construction industry
err2011-08-01
err136
PREAI
errKarimiAzari, AmirReza; Mousavi, Neda; Mousavi, S. Farid; Hosseini, SeyedBagher
err分享
err收藏
学者 查看更多内容