Construction Resource Allocation and Leveling Using a Threshold Accepting-Based Hyperheuristic Algorithm

delete2012-07-01
delete38
PRE
AI
G
Georgios K. Koulinas *
K
Konstantinos Anagnostopoulos
DOI:10.1061/(ASCE)CO.1943-7862.0000492delete
deleteOriginal
deleteOriginal request for help
deleteShare
deleteSave
Abstract

Abstract

En 中文
In this study we propose a threshold accepting based hyperheuristic for solving in a single run both the resource-constrained project scheduling problem or resource allocation, and the resource leveling problem. Having their roots in the field of artificial intelligence, hyperheuristics operate in the low-level heuristics domain rather than in the solutions domain. The hyperheuristic has been implemented within a commercial project management software package. Low-level heuristics operate on the solution domain defined by the priority values that the software uses for resource allocation. A case example from the literature and computational experiments on randomly generated projects demonstrate that the hyperheuristic achieves good performance in a timely manner, improving the results provided by the software. DOI: 10.1061/(ASCE)CO.1943-7862.0000492. (C) 2012 American Society of Civil Engineers.
Keywords:
Resource allocation
Resource leveling
Optimization
Construction management
Scheduling
AI Summary

AI Summary

Key information extracted from the uploaded paper, including a brief overview, abstract, background, key highlights, visual analysis, and future outlook.

Journal

J
Journal of Construction Engineering and Management
IF:
5.1
Papers:
5.1K
Citations:
1.4W

Organization

D
Democritus University of Thrace
Scholars:
4.8K
Papers: 3.7K
Citations: 3.8K