Eliminating Sub-Optimality in Earned Value Management Scheduling

delete2024-01-01
delete0
delete
OA
AI
C
C. Capone *
G
Gernot Kretzschmar
T
Timur Narbaev
DOI:10.1109/ACCESS.2024.3460535delete
delete原文链接
delete原文求助
delete分享
delete收藏
摘要

摘要

En 中文
Strategic and operational project successes rely on optimal implementation, with time-to-execution being a key value driver and competitive advantage. Earned Value Management (EVM) is the most pervasive approach to scheduling and cost monitoring in large-scale projects. Earned Schedule (ES) is a derivation of EVM that specifically addresses scheduling metrics, aiming to enhance the accuracy and relevance of time-based project assessments. However, prior research has shown that both EVM and ES may produce sub-optimal scheduling results. In addressing these challenges, our research aims to significantly reduce sub-optimality in EVM and ES schedules, meaning to methodically minimize inefficiencies within EVM processes, though recognizing that absolute optimality may not be achievable due to inherent project complexities. Specifically, this research demonstrates the common conditions under which top-down, ES metrics generate sub-optimal schedule assessments against the baseline. The purpose of our work is two-fold: First, we articulate why sub-optimality occurs. Second, utilizing our schedule variance path level metrics (SVP(t)), we address the ES limitation. The validity and practicality of our approach were demonstrated using three execution scenarios with simulation stress-tests. Our bottom-up approach considers schedule progress on critical and non-critical paths and utilizes total slack when necessary. Our results propose a tractable solution that improves schedule measurement accuracy, particularly in project environments with parallel activities and varying slacks. This enhancement is most significant in complex project topologies where traditional methods fall short, thereby underscoring the critical importance of detailed path-level analysis in scheduling across diverse tracking periods.
Keyword:
Earned schedule
earned value management
project monitoring and control
project schedule
schedule variance
total slack
critical path
path level variances
misleading project outcomes
earned value management
project monitoring and control
project schedule
schedule variance
total slack
critical path
path level variances
misleading project outcomes

期刊

IEEE Access 封面图
IEEE Access
IF:
3.6
论文数:
9.8W
被引数:
29.4W

机构

E
eada business school
学者数:
75
论文数: 127
被引数: 1
K
kazakh british technical university
学者数:
496
论文数: 274
被引数: 8
引用论文

引用论文

err分享
err收藏
学者 查看更多内容