New Delay-Analysis Method Using Modified Schedule and Modified Updated Schedule for Construction Projects

delete2022-11-01
delete8
PRE
AI
M
Murat ÇEVİKBAŞ
O
Ozan Okudan
Z
Zeynep Işık *
DOI:10.1061/(ASCE)CO.1943-7862.0002394delete
delete原文链接
delete原文求助
delete分享
delete收藏
摘要

摘要

En 中文
Being one of the most common dispute causes in construction projects, the delay is extremely important to be resolved promptly. To resolve delay-related disputes, delay analysis that is conducted to determine the amount of the delay that has occurred on a project together with its contractual responsible party is of paramount importance. Notwithstanding the numerous enhancements in the delay analysis domain, delay resolution remains one of the most challenging issues in construction projects due to various drawbacks of existing delay analysis methods. To minimize the delay-related issues in construction projects, this study, therefore, aims to develop a new delay analysis method that overcomes the drawbacks of existing delay analysis methods. The drawbacks of current methods were initially determined via an in-depth literature review and a focus group discussion (FGD) session conducted with seven experts experienced in the delay analysis domain. This step revealed that most of these methods ignore some critical features, such as consideration of critical path (CP), actual progress data, and fluctuations on CP. Moreover, most of the methods lack detailed numerical procedures and consider only the owner's delay. Furthermore, some types of activity relationships, actual improvements, and further delays made by contractors on the planned excusable compensable delay (ECD) and excusable noncompensable delay (END) are usually ignored by these methods. Then, a new delay analysis method, namely modified schedule versus modified updated schedule (MSvsMUS), was developed. To overcome the detected drawbacks, the proposed method is designed and developed in a way that can consider various activity relationships among the critical activities, include detailed numerical equations, and compute the variations between the modified schedule (MS) including planned fragnet/s and modified updated schedule (MUS) including actualized fragnet/s periodically. This was then followed by a case study conducted to demonstrate the method's mechanism. Finally, the developed method was evaluated and validated by conducting a second FDG session and a hypothetical case study. Results demonstrated that MSvsMUS has considerable potential to resolve delays and delay-related disputes escalated in construction projects.
Keyword:
Delay analysis
Extension of time
Claim
Modified schedule (MS)
Modified updated schedule (MUS)
Baseline schedule

期刊

J
Journal of Construction Engineering and Management
IF:
5.1
论文数:
5.1K
被引数:
1.4W

机构

Y
Yildiz Technical University
学者数:
5.7K
论文数: 5.3K
被引数: 42
I
Isparta University of Applied Sciences
学者数:
544
论文数: 491
被引数: 471
引用论文

引用论文

A lessons-learned tool for organizational learning in construction
err2020-02-01
err32
PREAI
errEken, Gorkem; Bilgin, Gozde; Dikmen, Irem; Birgonul, M. Talat
err分享
err收藏
err分享
err收藏
err分享
err收藏
An Overarching Review on Delay Analyses in Construction Projects
err2021-03-10
err41
errOAAI
errCevikbas, Murat; Isik, Zeynep
err分享
err收藏
Schedule Delay Risk Analysis in Construction Projects with a Simulation-Based Expert System
err2020-07-23
err26
errOAAI
errKoulinas, Georgios K.; Xanthopoulos, Alexandros S.; Tsilipiras, Thomas T.; Koulouriotis, Dimitrios E.
err分享
err收藏
学者 查看更多内容