Time/cost optimization using hybrid evolutionary algorithm in construction project scheduling
DOI:10.1016/j.autcon.2008.04.002.png)
摘要
En 中文
This paper deals with construction project scheduling. In the literature on the subject one can find such scheduling methods as: the Linear Scheduling Model (LSM), Line of Balance (LOB) charts and CMP/PERT network planning. The methods take into account several objective functions: the least cost, the least time, limited resources, work priorities, etc., both in the deterministic and probabilistic approach. The paper presents an analysis of the time/cost relationship, performed using time coupling method TCM III. A modified hybrid evolutionary algorithm (HEA) developed by Bozejko and Wodecki (A Hybrid Evolutionary Algorithm for Some Discrete Optimization Problems. IEEE Computer Society, 325-331, 2005) was used for optimization. (C) 2008 Elsevier B.V. All rights reserved.
Keyword:
Time coupling methods (TCM)
Hybrid evolutionary algorithm (HEA)
Time/cost relationship
AI总结
对已上传原文的论文进行重点信息的提取,主要内容包括:简要概述、研究摘要、背景介绍、关键亮点、图文解析、展望与总结。
期刊
IF:
11.5
论文数:
6.3K
被引数:
4.2W
机构
引用论文
Green manuring relocates microbiomes in driving the soil functionality of nitrogen cycling to obtain preferable grain yields in thirty years绿肥重新定位了微生物群,以驱动氮循环的土壤功能,从而在30年内获得更好的谷物产量
Microbicidal effects of weakly acidified chlorous acid water against feline calicivirus and Clostridium difficile spores under protein-rich conditions
PLOS ONE
IF0
Development and validation of a new method to quantify vitexin-2-O-rhamnoside on Passiflora L. extracts开发和验证量化西番莲提取物vitexin-2-O-rhamnoside的新方法
Wind-proof and sand-fixing effects of Artemisia ordosica with different coverages in the Mu Us Sandy Land, northern China中国北方毛乌素沙地不同覆盖率的蒿的防风固沙作用