A batch scheduling model for m heterogeneous batch processor

delete2015-06-17
delete8
PRE
AI
N
Nita P.A Hidayat *
A
Andi Cakravastia
T
T.M.A. Ari Samadhi
A
Abdul Hakim Halim
DOI:10.1080/00207543.2015.1056322delete
deleteOriginal
deleteOriginal request for help
deleteShare
deleteSave
Abstract

Abstract

En 中文
This research addresses a batch scheduling problem for single item parts with multi due date on m heterogeneous batch processors. The objective is to minimise total actual flowtime of parts through the shop. The total actual flowtime of parts in a batch is the multiplication of the interval between batch arrival time and the due date by the number of parts in the batch. Using the actual flowtime as the objective means it is oriented to satisfy the due date as a commitment to customers, and simultaneously to minimise the length of time of the parts spending in the shop. An algorithm to solve this problem is proposed.
Keywords:
actual flowtime
batch processor
batch scheduling
AI Summary

AI Summary

Key information extracted from the uploaded paper, including a brief overview, abstract, background, key highlights, visual analysis, and future outlook.

Journal

International Journal of Production Research cover
International Journal of Production Research
IF:
7.3
Papers:
1.1W
Citations:
3.7W

Organization

I
institute technology of bandung
Scholars:
5.0K
Papers: 2.9K
Citations: 1
Cited Papers

Cited Papers

errShare
errSave
err
IF0
err
err0
PREAI
err
errShare
errSave
researcher View more