AN EARNED-VALUE-ANALYSIS (EVA)-BASED PROJECT CONTROL FRAMEWORK IN LARGE-SCALE SCAFFOLDING PROJECTS USING LINEAR REGRESSION MODELING

delete2022-07-07
delete2
delete
OA
AI
Z
Zhen Lei *
Y
Yongde Hu
J
Jialiang Hua
B
Brandon Marton
N
Noah Marton Peter Goldberg
N
Noah Marton
DOI:10.36680/j.itcon.2022.031delete
deleteOriginal
deleteOriginal request for help
deleteShare
deleteSave
Abstract

Abstract

En 中文
In large-scale industrial construction projects, scaffolding activities account for a large amount of the construction budget, and overlooking the scaffolding management can lead to budget overruns and schedule delays. The scaffolding activities can be categorized by classifications and types based on the nature of the scaffold builds. To ensure the project progress on track, it is critical to measure project performance based on project progress data. However, given the nature of scaffolding activities, it has been challenging to track and utilize the scaffolding data for analytical purposes. Therefore, this paper proposes a project control framework based on Earned-value analysis (EVA), in which linear regression models are used for productivity prediction. Three scenarios of productivity based on historical data (i.e., low, medium, and high productivity) are introduced. The proposed framework is implemented in a real construction project for validation. The results have shown that the proposed framework can efficiently evaluate the project progresses integrated with the EVA. The construction companies, such as general contractors and scaffolding sub-contractors, can use this method for site progress tracking. For future work, the EVA can be integrated with other non-linear predictive models (e.g., neural network) for productivity prediction. The EVA results can be integrated with data visualization to create situational awareness for construction practitioners.
Keywords:
scaffolding management
regression models
project control
earned-value analysis

Journal

J
Journal of Information Technology in Construction
IF:
3.8
Papers:
285
Citations:
1.6K

Organization

U
University of New Brunswick
Scholars:
4.0K
Papers: 4.2K
Citations: 6.3K