Harmony search algorithm for single-machine scheduling problem with planned maintenance

delete2014-10-01
delete46
PRE
AI
F
Francesco Zammori *
M
Marcello Braglia
D
Davide Castellano
DOI:10.1016/j.cie.2014.08.001delete
deleteOriginal
deleteOriginal request for help
deleteShare
deleteSave
Abstract

Abstract

En 中文
This paper focuses on the single machine scheduling problem, with sequence dependent setup times. Both processing and setup times are deterministic and the objective is to minimize total earliness and tardiness penalties. The novelty of the model can be traced in the fact that the single machine is subjected to breakdowns and that, in order to increase its availability, planned maintenance tasks are also performed. Hence, jobs and maintenance tasks are jointly considered to find the optimal schedule. These features make the problem NP-hard and so, a quasi-optimal solution is searched using a recent metaheuristic, which integrates harmony search and genetic algorithms. In order to validate the proposed metaheuristic, a comprehensive set of scheduling problems was fully investigated. Obtained results, compared with those of exhaustive (for small problems) and standard metaheuristics, confirm both the robustness and the speed of the proposed approach. (C) 2014 Elsevier Ltd. All rights reserved.
Keywords:
Earliness-tardiness penalties
Harmony search
Metaheuristics
Planned maintenance
Scheduling
Single machine
AI Summary

AI Summary

Key information extracted from the uploaded paper, including a brief overview, abstract, background, key highlights, visual analysis, and future outlook.

Journal

Computers and Industrial Engineering cover
Computers and Industrial Engineering
IF:
6.5
Papers:
1.0W
Citations:
3.8W

Organization

U
University of Parma
Scholars:
1.7W
Papers: 1.3W
Citations: 1.3W
U
University of Pisa
Scholars:
3.1W
Papers: 2.4W
Citations: 2.4W