Mixed-integer linear programming for resource leveling problems

delete2012-08-01
delete105
PRE
AI
J
Julia Rieck *
J
Jürgen Zimmermann
T
Thorsten Gather
DOI:10.1016/j.ejor.2012.03.003delete
deleteOriginal
deleteShare
deleteSave
Abstract

Abstract

En 中文
We consider project scheduling problems subject to general temporal constraints, where the utilization of a set of renewable resources has to be smoothed over a prescribed planning horizon. In particular, we consider the classical resource leveling problem, where the variation in resource utilization during project execution is to be minimized, and the so-called overload problem, where costs are incurred if a given resource-utilization threshold is exceeded. For both problems, we present new mixed-integer linear model formulations and domain-reducing preprocessing techniques. In order to strengthen the models, lower and upper bounds for resource requirements at particular points in time, as well as effective cutting planes, are outlined. We use CPLEX 12.1 to solve medium-scale instances, as well as instances of the well-known test set devised by Kolisch et al. (1999). Instances with up to 50 activities and tight project deadlines are solved to optimality for the first time. (C) 2012 Elsevier B.V. All rights reserved.
Keywords:
Project scheduling
Resource leveling
Minimum and maximum time lags
Lower and upper bounds
Cutting planes

Journal

European Journal of Operational Research cover
European Journal of Operational Research
IF:
6
Papers:
2.2W
Citations:
8.1W

Organization

T
tu clausthal
Scholars:
26
Papers: 12
Citations: 1.1K
Cited Papers

Cited Papers

Regulatory T cells in spontaneous autoimmune encephalomyelitis
err2002-03-14
err0
PREAI
errGláucia De Camargo Furtado; Danyvid Olivares‐Villagómez; Maria A. Curotto de Lafaille; Allen K. Wensky; Jo‐Ann Latkowski; Juan J. Lafaille
errShare
errSave
errShare
errSave
errShare
errSave
CCD: Efficient Customized Content Dissemination in Distributed Publish/Subscribe
err2009-01-01
err0
errOAAI
errHojjat Jafarpour; Bijit Hore; Sharad Mehrotra; Nalini Venkatasubramanian
errShare
errSave
Event-based MILP models for resource-constrained project scheduling problems
err2011-01-01
err147
errOAAI
errKone, Oumar; Artigues, Christian; Lopez, Pierre; Mongeau, Marcel
errShare
errSave
researcher View more