On linear lower bounds for the resource constrained project scheduling problem

delete2003-09-01
delete34
PRE
AI
J
Jacques Carlier *
N
Néron, E
DOI:10.1016/S0377-2217(02)00763-4delete
deleteOriginal
deleteOriginal request for help
deleteShare
deleteSave
Abstract

Abstract

En 中文
The aim of this paper is to propose efficient methods for solving the resource constrained project scheduling problem (RCPSP). These methods are based on makespan lower bounds, which linearly depend on the processing times of the activities. Linear lower bounds (LLB) can be obtained in different ways. The first application that we present is a general linear programming scheme for computing a makespan lower bound. The second application consists in associating redundant resources with LLB. Consequently we get new adjustments of release dates and tails of the project activities. These adjustments are tight for certain RCPSP instances, as shown by our computational results. (C) 2003 Published by Elsevier Science B.V.
Keywords:
resource constrained project scheduling
linear programming
lower bounds
redundant resources
AI Summary

AI Summary

Key information extracted from the uploaded paper, including a brief overview, abstract, background, key highlights, visual analysis, and future outlook.

Journal

European Journal of Operational Research cover
European Journal of Operational Research
IF:
6
Papers:
2.2W
Citations:
6.4W

Organization

No organization information available