Industrial environments frequently face disruptive events. This contribution presents a support framework, aimed at addressing the repair-based reactive scheduling problem. It is based on an explicit object-oriented domain representation and a constraint programming (CP) approach. When an unforeseen event occurs, the framework captures the in-progress agenda status, as well as the event effect on it. Based on this information, a rescheduling problem specification is developed. Tasks to be rearranged are recognized and the set of the most suitable rescheduling action types (e.g. shift-jump, reassign, freeze) is identified. Since a given specification may lead to several solutions, the second stage relies on a CP model to address the problem just defined. To create such model, action types are automatically transformed into constraints. Provided that good quality schedules can be reached in low CPU times, alternative solution scenarios focusing on stability and regular performance measures can be posed for each problem. (C) 2010 Elsevier Ltd. All rights reserved.
Keywords:
Reactive scheduling
Batch plants
Decision support systems
Knowledge-based scheduling
Constraint programming
AI Summary

AI Summary

Key information extracted from the uploaded paper, including a brief overview, abstract, background, key highlights, visual analysis, and future outlook.

Journal

C
Computers and Chemical Engineering
IF:
3.9
Papers:
8.1K
Citations:
1.7W

Organization

National University of the Littoral cover
National University of the Littoral
Scholars:
3.4K
Papers: 2.4K
Citations: 2.0K
Cited Papers

Cited Papers

errShare
errSave
errShare
errSave
Arm MILP-based reordering algorithm for complex industrial scheduling and rescheduling
err2001-05-01
err71
PREAI
errRoslöf, J; Harjunkoski, I; Björkqvist, J; Karlsson, S; Westerlund, T
errShare
errSave
Production scheduling of a large-scale industrial batch plant. II. Reactive scheduling
err2006-05-28
err111
PREAI
errJanak, Stacy L.; Floudas, Christodoulos A.; Kallrath, Josef; Vormbrock, Norbert