Spatial analysis and complexity evaluation for predicting rebar installation duration

delete2025-08-19
delete0
delete
OA
AI
F
Fabian Pfitzner *
A
Alexander Braun
A
André Borrmann
F
Frédéric Bosché
DOI:10.1016/j.autcon.2025.106462delete
deleteOriginal
deleteShare
deleteSave
View PDF
Abstract

Abstract

En 中文
• Grid-based spatial analysis quantifies activity complexity-duration relationships in construction. • CV-based activity classification architecture (ViTPoseActivity) achieves 97% detection accuracy. • BIM-derived complexity metrics enable localized correlation analysis for proactive planning. • Analysis of 1,900+ labor hours in rebar installation confirms measurable activity complexity-duration correlation.
Keywords:
Spatial analysis
Labor productivity
Activity classification
Activity complexity
AI Summary

AI Summary

Key information extracted from the uploaded paper, including a brief overview, abstract, background, key highlights, visual analysis, and future outlook.

Journal

Automation in Construction cover
Automation in Construction
IF:
11.5
Papers:
6.2K
Citations:
4.2W

Organization

T
Technische Universität München
Scholars:
231
Papers: 96
Citations: 0
U
University of Edinburgh
Scholars:
5.1W
Papers: 4.6W
Citations: 71