Multiobjective Optimization Model for Planning Repetitive Construction Projects

delete2021-07-01
delete26
PRE
AI
A
Ayman Altuwaim *
K
Khaled El‐Rayes
DOI:10.1061/(ASCE)CO.1943-7862.0002072delete
delete原文链接
delete原文求助
delete分享
delete收藏
摘要

摘要

En 中文
Minimizing the duration of repetitive construction projects such as high-rise buildings and highway construction often requires interrupting the work continuity of construction crews and/or utilizing overtime hours. Available scheduling models for repetitive construction projects can generate optimal trade-offs between minimizing project duration and crew work interruptions; however, they are incapable of minimizing the use of overtime hours. This paper developed a novel multiobjective optimization model for repetitive construction projects that is capable of generating optimal trade-offs among project duration, work interruptions, and overtime use. The model was developed in three main phases (1) a formulation phase that identified all relevant decision variables and formulated the three objective functions of the model; (2) an implementation phase that executed the model computations using multiobjective genetic algorithms; and (3) a performance evaluation phase. The results of this performance evaluation confirmed that the model outperforms existing models in minimizing the use of overtime hours, and generating optimal trade-offs among project duration, crew work interruptions, and overtime use. (C) 2021 American Society of Civil Engineers.
Keyword:
COST OPTIMIZATION
CPM/LOB
LINE
CPM

期刊

J
Journal of Construction Engineering and Management
IF:
5.1
论文数:
5.1K
被引数:
1.4W

机构

K
King Saud University
学者数:
3.4W
论文数: 3.8W
被引数: 815
University of Illinois System 封面图
University of Illinois System
学者数:
6.9W
论文数: 6.2W
被引数: 644
引用论文

引用论文

学者 查看更多内容