Optimization model for resource assignment problems of linear construction projects

delete2007-07-01
delete59
PRE
AI
S
Shu‐Shun Liu *
C
Chang‐Jung Wang
DOI:10.1016/j.autcon.2006.08.004delete
delete原文链接
delete原文求助
delete分享
delete收藏
摘要

摘要

En 中文
For linear construction projects, it has long been known that resource utilization is important in improving work efficiency. However, most existing scheduling techniques cannot satisfy the need for solving such issues. This study presents a flexible model for resolving linear scheduling problems involving different objectives and resource assignment tasks. The proposed model adopts constraint programming (CP) as the searching algorithm for model formulation, and CP program implemented in this study creates the flexibility for optimizing either total cost or project duration. Additionally, the concept of outsourcing resources is introduced here to improve project performance. A bridge project from pertinent literature is selected, and model validation and two scenarios are conducted to demonstrate the model capability. According to the research results, consideration of outsourcing resources not only helps achieve diversity of resource supply but also creates a positive influence on the optimum solution by simultaneously reducing time and cost. (C) 2006 Elsevier B.V All rights reserved.
Keyword:
linear construction projects
linear scheduling
resource assignment
constraint programming
outsourcing resources
AI总结

AI总结

对已上传原文的论文进行重点信息的提取,主要内容包括:简要概述、研究摘要、背景介绍、关键亮点、图文解析、展望与总结。

期刊

Automation in Construction 封面图
Automation in Construction
IF:
11.5
论文数:
6.3K
被引数:
4.2W

机构

暂无机构信息
引用论文

引用论文

err分享
err收藏
err分享
err收藏
学者 查看更多内容