Solving single batch-processing machine problems using an iterated heuristic

delete2011-07-15
delete17
PRE
AI
H
Huimei Wang *
DOI:10.1080/00207543.2010.518995delete
delete原文链接
delete原文求助
delete分享
delete收藏
摘要

摘要

En 中文
This article considers the problem of minimising total weighted tardiness on a batch-processing machine with compatible product families, job release dates and non-identical job sizes. A batch-processing machine can process several jobs as long as the total size of jobs in the batch does not exceed the machine's capacity. All jobs in the batch are started and completed at the same time. Batch processing time is equal to the longest job processing time among jobs in the batch. This article proposes a two-phase heuristic, in which a population-based reasoning approach is developed to determine the sequence of jobs based on their intensity values at positions in the first phase, and a dynamic programming algorithm to divide the ordered jobs into batches sequentially. An iterated heuristic is also proposed to improve solution quality further. Computational results show that high-quality solutions can be obtained by the proposed heuristic algorithms in a very short time.
Keyword:
batch-processing machine
total weighted tardiness
scheduling
AI总结

AI总结

对已上传原文的论文进行重点信息的提取,主要内容包括:简要概述、研究摘要、背景介绍、关键亮点、图文解析、展望与总结。

期刊

International Journal of Production Research 封面图
International Journal of Production Research
IF:
7.3
论文数:
1.1W
被引数:
3.7W

机构

暂无机构信息
引用论文

引用论文

Electromyographic changes in myasthenia gravis
err1955-11-01
err0
PREAI
errRichard J. Johns; David Grob; A. McGehee Harvey
err分享
err收藏
Scheduling a capacitated batch-processing machine to minimize makespan
err2007-04-01
err25
PREAI
errDamodaran, Purushothaman; Srihari, Krishnaswami; Lam, Sarah S.
err分享
err收藏
err分享
err收藏
学者 查看更多内容