Analytical framework for delay analysis implementation system
DOI:10.1108/ecam-04-2026-0636.png)
Abstract
En 中文
Purpose
The objective of this study is to develop an analytical framework for delay analysis implementation system (DAIS) that can perform any method of delay analysis using an Excel-based system while explicitly addressing complicated factors such as float ownership, the treatment of concurrent delays, critical path shifts, multiple calendars and contractual constraints.
Design/methodology/approach
Delay analysis tools are driven by static, dynamic, additive and subtractive methods. While each method has distinct strengths, it also has some limitations. The calculations involved in DAIS are performed in a Microsoft Excel-based spreadsheet, which automate the implementation of any of the delay analysis methods through a series of mathematical functions and numerical computations.
Findings
DAIS quantifies project delays and assigns responsibility to the appropriate party. It facilitates granting time extensions and determining liquidated damages. DAIS has been tested in a case and the outcomes are satisfactory.
Originality/value
No systematic effort has ever been made to establish foundations for an automated system capable of performing each of the four methods of delay analysis and therefore replacing existing labor-intensive and error-prone manual practices. DAIS addresses this gap by providing a reliable, efficient, economical, consistent, transparent and reproducible framework for conducting delay analysis.
Keywords:
Delay analysis
Analytical framework
Project scheduling
Time extension
Journal
E
IF:
3.9
Papers:
96
Citations:
10
Organization
Cited Papers
Enhancing Forensic Analysis of Construction Project Delays Through Digital Interventions
Buildings
IF0