Role of Statistics and Engineering Judgment in Developing Optimized Time-Cost Relationship Models

delete2014-08-01
delete7
PRE
AI
V
Vítor Sousa *
N
N. Almeida
L
Luís Alves Dias
DOI:10.1061/(ASCE)CO.1943-7862.0000874delete
deleteOriginal
deleteOriginal request for help
deleteShare
deleteSave
Abstract

Abstract

En 中文
When estimating the duration of the construction stage during the design stages of construction projects, empirical models are often used as a substitute for more accurate estimates based on detailed scheduling. These models, traditionally designated as time-cost relationships (TCR), derive from regressions relating the duration of concluded construction projects with characteristics that can be easily foreseen during the planning and design stagesboth quantitative (e.g.,cost, gross floor area, number of floors) and qualitative (e.g.,type of contract). This paper reviews the approaches that have been adopted to develop the TCR models and discusses the complementary roles that statistics and engineering judgment can play towards their optimization and enhanced accuracy. This discussion includes the statistical and practical implications of (1)the quantitative independent variables used, (2)the qualitative independent variables used, and (3)the mathematical structure used. The paper aims at demonstrating the importance of sound statistics and highlights some of the most common mistakes. Additionally, it provides illustrative examples to show the complementary role that engineering judgment should have in the process of developing more robust, reliable, and accurate statistical-based TCR.
Keywords:
Construction management
Project management
Scheduling
Construction costs
Statistics
Time factors
Construction project scheduling
Time-cost relationship
Regression
Statistics
Engineering judgment
Cost and schedule

Journal

J
Journal of Construction Engineering and Management
IF:
5.1
Papers:
5.1K
Citations:
1.4W

Organization

U
universidade de lisboa
Scholars:
3.4W
Papers: 3.1W
Citations: 29