Comparing optimization modeling approaches for the multi-mode resource-constrained multi-project scheduling problem

delete2019-11-11
delete17
PRE
AI
M
Marimuthu Kannimuthu *
B
Benny Raphael
E
Ekambaram Palaneeswaran
A
Ananthanarayanan Kuppuswamy
DOI:10.1108/ECAM-03-2019-0156delete
delete原文链接
delete原文求助
delete分享
delete收藏
摘要

摘要

En 中文
Purpose Construction firms keep minimal resources to maintain productive working capital. Hence, resources are constrained and have to be shared among multiple projects in an organization. Optimal allocation of resources is a key challenge in such situations. Several approaches and heuristics have been proposed for this task. The purpose of this paper is to compare two approaches for multi-mode resource-constrained project scheduling in a multi-project environment. These are the single-project approach (portfolio optimization) and the multi-project approach (each project is optimized individually, and then heuristic rules are used to satisfy the portfolio constraint). Design/methodology/approach A direct search algorithm called Probabilistic Global Search Lausanne is used for schedule optimization. Multiple solutions are generated that achieve different trade-offs among the three criteria, namely, time, cost and quality. Good compromise solutions among these are identified using a multi-criteria decision making method, Relaxed Restricted Pareto Version 4. The solutions obtained using the single-project and multi-project approaches are compared in order to evaluate their advantages and disadvantages. Data from two sources are used for the evaluation: modified multi-mode resource-constrained project scheduling problem data sets from the project scheduling problem library (PSPLIB) and three real case study projects in India. Findings Computational results prove the superiority of the single-project approach over heuristic priority rules (multi-project approach). The single-project approach identifies better solutions compared to the multi-project approach. However, the multi-project approach involves fewer optimization variables and is faster in execution. Originality/value An integer programming model was developed in this research to optimize the multiple objectives in a multi-project environment considering explicit resource constraints and maximum daily costs constraints. This model was used to compare the performance of the two multi-project environment approaches. Unlike existing work in this area, the model used to predict the quality of activity execution modes is based on data collected from real construction projects.
Keyword:
Optimization
Scheduling
Project management
Decision support systems
Construction planning
AI总结

AI总结

对已上传原文的论文进行重点信息的提取,主要内容包括:简要概述、研究摘要、背景介绍、关键亮点、图文解析、展望与总结。

期刊

J
Journal of Construction Engineering and Management
IF:
5.1
论文数:
5.1K
被引数:
1.4W

机构

I
indian institute of technology (iit) - madras
学者数:
5.1K
论文数: 5.2K
被引数: 1
I
indian institute of technology system (iit system)
学者数:
9.5W
论文数: 9.9W
被引数: 93
引用论文

引用论文

err
IF0
err
err0
PREAI
err
err分享
err收藏
An Automated Image Processing Module for Quality Evaluation of Milled Rice
err2023-03-16
err0
errOAAI
errChinmay Kurade; Maninder Meenu; Sahil Kalra; Ankur Miglani; Bala Chakravarthy Neelapu; Yong Yu; Hosahalli S. Ramaswamy
err分享
err收藏
学者 查看更多内容